About the project
A client in the pharmaceutical sector required the installation of a new auto blowdown valve as part of their ongoing boiler upgrade works. The goal was to improve control over boiler water quality and ensure consistent blowdown cycles without manual intervention.
Project goals
Our engineering team removed the existing pipework to allow for the integration of the new auto blowdown system. This included:
All works were completed in line with site safety standards and relevant boiler operation requirements.
Our solutions
The new auto blowdown valve is now fully operational, providing automated blowdown control as intended. This ensures a consistent and efficient removal of boiler water impurities, reducing the need for manual checks and improving overall boiler performance. The result is a more controlled system that supports reliability, efficiency, and ongoing boiler health.