SUCCESSFUL HOSPITAL INSTALL AGAINST THE CLOCK

Friday May 29 2020

JBC Mechanical Services had only 12 hours to remove an existing steam meter at Leeds General Infirmary and install all the new pre-fabricated spools and valves, including 2 x 12” parallel slide valves with a bleed valve arrangement in its place and an 8” tee off the line with a further 2 x 8” parallel slide valves to allow an inlet point when the temporary boilers went on line.  A spider crane was used to lift the heaviest item weighing 380kg. 

The install was completed in good time and the hospital was back on line well within the 12-hour window. 